Now that the floor on the main floor is decked we were able to get the walls up. We did this on the 10
th and the 11
th.

Luckily we had the help because we built the walls on the ground then put the sheeting and
Tyvek on and lifted them into place. Now I don't have to get on a ladder to put the sheeting on.


View of the back from the lake. Remember we still have on more floor to go.


This weekend (17
th and 18
th) we got the main beam on the main floor up and all the floor joists. Next step, putting the floor sheeting down. Hopefully we will have the walls up after Thanksgiving.