Wednesday, October 3, 2007

Late Update

I know it's been a while but here's the latest...

We finished all the Polysteel blocks so all the walls are at 11 feet. We have been working at setting the vertical rebar and tying it up. Next step is to get an ininspection and figure out where I need to put pipes through the wall for power, water and sewer. I need to make sure all this is through before we pour the concrete otherwise I will end up wasting a weekend drilling through the walls to put a pipe in.







Well, Perry Excavating called and wanted to know if they could spen a day and bring in some dirt.


I have no idea how many loads were brought in but I do know that there will be many more once we pour the wall and get the garage floor on.