Then on Sunday Doug and I spent the day putting up the hip trusses of the garage side of the roof, finishing up some corners and figuring out how to get the valleys framed in. In the next day or so we should be getting the overhang framed above the bedroom(left side on the pic below) and getting the eves trimmed back so we can set the 2 X 6. and who knows we may even get some of the plywood up!
Monday, December 31, 2007
Roof is coming along
Then on Sunday Doug and I spent the day putting up the hip trusses of the garage side of the roof, finishing up some corners and figuring out how to get the valleys framed in. In the next day or so we should be getting the overhang framed above the bedroom(left side on the pic below) and getting the eves trimmed back so we can set the 2 X 6. and who knows we may even get some of the plywood up!
Monday, December 10, 2007
If only the weather would cooperate
During the week last week there were quite a bit of walls going up on the first floor. Above you can see the entry closet and the study wall along the staircase.
I was able to finish up the pantry walls this week. Next set of walls to go up will be the bathroom and the other wall along the staircase.
Here is the wood that is left for the garage, the sheeting for the roof, and the remaining roof trusses to be put up. We are going to see if a few people are able to get the trusses upstairs but if cannot we'll get the marks on the top plate and hire a crane to come out and lift the few we can't do by hand.
Friday, November 30, 2007
Second floor just about there
Here your are seeing where the staircase will be going upstairs. To the left will be closet and office. Obviously to the left of that is the front door.
This weekend is going to be hectic since they are predicting 6" - 12" of snow. We'll see how accurate they are.
Monday, November 19, 2007
Finally out of the Basement
Friday, November 9, 2007
One more step
Thursday, November 8, 2007
Progress!
Tuesday, October 30, 2007
Bassement floors are now poured!
Tuesday, October 16, 2007
The day of the pour...
Below is Dan and Rich going to fix a wall before we get anymore blowouts.
Ed is making sure that I had all the tie wires nice and tight so our T-walls wouldn't seperate during the pour.
I'm showing Jeremy what to look for while pumping the concrete into the walls. Dan is securing the corner with tie wire through the 2 X 6 corners so hopefully we don't have any seperations. He must have done alright because that corner held!!
Jim is feeling how far up the wall the concrete is. We were trying to go 3 feet at a time so we wouldn't have too much weight in one spot.
Break time waiting for the concrete trucks to switch spots. The end at last. The next couple pictures are us finishing the top of the walls.
And the final product!!!! Free standing walls. the picture below you can see that there are steel studs sticking out in the garage area. These will be used once the prestressed planks are set. I will screw 2 inch foam and half inch OSB to them to create a wall so the topping on the prestressed doesn't flow down the side of the wall and it acts as a fake rim joist that way we will have something to secure the siding to.
The pour itself went from noon to 4 o'clock and took 66 yards of concrete. It may have took about a month to get to this part but I am glad I did it this way and not normal cement blocks!
Wednesday, October 10, 2007
Basement wall pour
On Monday the prestressed concrete (Molin) is coming out to get a final measurement for the garage floor and the front stoop.
We will have pictures from the pour on Friday when we're done.
Friday, October 5, 2007
Next Milestone Passed!!!
Wednesday, October 3, 2007
Late Update
We finished all the Polysteel blocks so all the walls are at 11 feet. We have been working at setting the vertical rebar and tying it up. Next step is to get an ininspection and figure out where I need to put pipes through the wall for power, water and sewer. I need to make sure all this is through before we pour the concrete otherwise I will end up wasting a weekend drilling through the walls to put a pipe in.
Well, Perry Excavating called and wanted to know if they could spen a day and bring in some dirt.
Monday, September 17, 2007
Getting close
Nearing the end of the day we had almost 10 feet of wall up all the way around. We we're missing the 1 foot high corner blocks. Hopefully they show up tonight then I could have the garage all done and only have to consentrate on the house.
Here I am putting the ten foot high course on. This weekend we we're able to get all the inside bracing put up so I can walk all the way around and set blocks. I have to say that if it wasn't for Doug, Dan and my dad I would still be there putting up bracing and only working on the 6 foot course of block. Thanks guys!
I can't wait until I can sit in my basement and enjoy this view of the lake.
Less than a year away!!!!!!!!!